Bilfinger Turnaround Concept

Bilfinger Turnaround Concept

Client / Site / Project: Equinor / Mongstad / TAR 2019 Heat exchangers & air coolers

Scope of services:

  • Overall planning of Heat exchanger and air cooler services
  • Project management and site supervision, HSE coach, Quality management & Administration
  • Time scheduling & progress monitoring
  • Inspection services
  • Cleaning services
  • Internal transport services
  • Coordination of all involved disciplines:
  • Inspection, cleaning, cranes, scaffolding, insulation and internal transports  
  • Mechanical overhauling work of Heat exchangers and air coolers
  • Demounting/mounting of Heat exchangers using two Extractor teams (one self-propelled extractor)
  • Bolt tensioning following Clients specifications
  • Pressure testing of Heat exchangers after completion
  • Welding repair work of Heat exchangers after inspections

Execution Phase: September, 2019 – October, 2019; duration 6 weeks

Workforce: 95 persons (~35 000 hours)

Kontaktperson

Mattias Johansson

Mattias Johansson

Avd. chef Mek
Underhållscenter
Project & Maintenance

Mobil: 0708-649273

mattias.johansson*Den Text zwischen den * loeschen, dies ist ein Spamschutz*@bilfinger.com
Skriv ut